House update #20

Mainly because the floors are going to take 3+ days to stain/cover/dry, we changed our move date 7 days. November 1, ladies and gents, is the big day.

Thursday 10/10: laundry pass-thru, place mailbox, driveway gate location, documents for flood insurance, audio visual system begging to get trimmed out, gutters getting installed, more tile backsplash, plumbers putting in faucets, painters working, Madeval adjusting kitchen cabinets for appliances

Friday 10/11: style of outlet covers, exterior light trim kit, select artificial grass, locations for usb-c outlets, place master barn door handles, lots of electricians – can lighting going in

Saturday, 10/12: gutter install, decking in backyard, painting continues, more electric and plumbing, mailbox in place

Monday, 10/14: Meeting with landscaper to decide lighting, oak tree placement, final garden design and plants. It is going to be so amazing – I’m excited. The representative delivering the oak tree laughed at me that she should bring it on Saturday. She said we’d never be ready.

Tuesday, 10/15: Selected floor stain

Wednesday, 10/16: Mr. B spent time with the cable guys. I was away all day and went over around 4pm to see downstairs lighting being installed. Holy smokes! I was blown away.

Related Posts Plugin for WordPress, Blogger...

One response

  1. Those lights are awesome! I know I’ve said this before, but your new house is such a work of art, very impressive. It’s going to be so exciting to move in.

Leave a Reply

Your email address will not be published. Required fields are marked *

Discover more from Poetic Aperture

Subscribe now to keep reading and get access to the full archive.

Continue reading